Just got back from Borovets after spending a few days fact-finding and sourcing furniture. I found an excellent shop in Sofia for the furniture called Yavor, it may be of use for you to note that the apertures for the wardrobes are 182cms wide - Yavor do wardrobes of exactly this width - I don't know if the standard furniture packs include this size of wardrobe, it seems too much of a coincidence they happen to be the right size so they are probably the same manufacturer.
Work on the complex has progressed well, it is probably about 85%
complete. I am very surprised that Act 15 is being signed today, as
yesterday there were still unfinished items in my apartment:
1) No kitchen units fitted
2) No skirting fitted around the edge of the floors in any of the
rooms.
The main infrastructure is far from complete - the lift is not
operational, there is no reception area furnishing or restaurant
fittings etc. and the exterior landscaping still has a way to go.
There is no water in the swimming pool yet. The whole building needs a
thorough clean, but this would obviously not happen until all the works are completed.
I did not know they have only built blocks C & D, the rest have been shelved because of the slump in demand. The building still looks quite impressive though.
I am going to request more time to pay, leaving a percentage until 2nd week of December. Hopefully this will see Act 16 in place.