Panorama Casino & Spa

Status
Not open for further replies.
J

Juliette

New Member
Hi, has anyone bought in Panorama Casino & Spa in Bansko? There are delays in completion of blocks A & B & also some of the surrounding areas. Any info please? Thanks a lot
 
O

olliesdad

New Member
Hi, has anyone bought in Panorama Casino & Spa in Bansko? There are delays in completion of blocks A & B & also some of the surrounding areas. Any info please? Thanks a lot
Juliette,

Hi, we have bought a 1 bed appt in C block and my parents have bought one in D block. We were told the property would be completed by 30/10 and have recently received a request for the final payment as Act 15 has been served. We have made an arrangement to visit next week (11th - 13th Dec) but have now been told by the developers that the appartments are not yet complete. I would be interested to hear how everyone else is doing...
 
T

Tim Timovic

New Member
Hi Juliette / Olliesdad,

We've bought in block A, but are similarly uninformed about building progress. Our agent requested final pymts mid-Nov, but we didn't pay since our lawyer informed that act 15 had not been granted. Other investors have suggested to us that completion would still appear to be some time off.

I'll be willing to share info as I get it.

Regards,
Tim
 
O

olliesdad

New Member
Well, we bought ours through avatar and they also informed us that the development wasn't complete and to hold off. I'm going out tomorrow to see whats going on and will post a message when i get back on Friday.
 
J

Juliette

New Member
I rang our lawyer in Bulgaria & she said that Blocks C&D are completed & act 15 cert issued. Is that right for those of you who bought in blocks C&D? Have you [paid the balance yet? For Block B act 15 cert should be issued in around 2 weeks. Block A act 15 cert in January or possibly end dec. She said that the reason for the delays is that the mayor of bansko stopped all development work in bansko for 3 months. The surrounding areas ie: pool, restaurant, reception etc will not be ready until april. Our apartment will have an act 15 certificate issued in about 2 weeks & the inside will be ready, elevators, water & electric. The last document for the complex is an act 16 habitation certificate which should be issued within 33 days of the act 15, but these are always late because not enough people work in the offices & bansko has so many developments. We become the owners with act 15 & we need to pay then, think it was within 14 days, but legally we shouldn’t rent the apartment without the habitation cert, although she said many complexes do. I said I wouldn’t be happy with that ie: if someone had an accident etc. Aparently the developer tried to catch up on the work with extra workers but has been unable to. I asked what happens if the developer just never finishes it off & we have paid & she said that it is in their interest to complete asap as they will be making a profit by managing most of the apartments through Top Property management, owned by same people as STC. Also, they have plenty of money & 2 other complexes are currently under construction. Good quality materials have been used & the view is beautiful apparently (although I imagine still building work going on!). it is one of the biggest complexes in bansko. Any comments about paying prior to the surrounding areas being completed? Also we tried for compensation but were told as the delay was outside the control of the developer we would not be entitled & that this is stated in the contract.
 
O

olliesdad

New Member
Juliette / tim,

I got back at 3am from Bansko so this is just a brief message. I will hopefully find some way of uploading some photos for you later. Basically, the structure is complete but the development is not finished by any standard. Blocks C and D are far more advanced and theoutside is rendered and cladded and looks very good. Inside, some rooms have laminate flooring down and are plastered. Most rooms in D block have fitted bathrooms. The most striking aspect is how incomplete the rest is. The lift shafts are empty and all stair cases are bare concrete.

Our legal rep from Ralitsa Galiva (throught fidentia) state that we should hold off final payment as it is perhaps 3 months until it will be habitable.

I will try to get a link to some photos and will post a message when I have worked out how to do this.

Tim, where have you been contacted by other investors?

regards.
 
J

Juliette

New Member
thanks for this olliesdad. we are using the same lawyer (Ralitsa) but not through Fidentia/Avatar. she told us we would need to pay in the next couple of weeks - although our block is far less complete then yours. the info above from me was from a phone call with her. we have not had any written advice of the delay from the developers & we actually only found out about it from the furnishings company we planned to send in to measure up. What are your thoughts on the whole situation? If this delay was due to the mayor stopping work then surely loads of other builds are late? Did you get to speak to the developer? What did Avatar say? etc... Thanks
 
O

olliesdad

New Member
I have loaded some pics on but can't paste the link into this blog for some reason. i'll get back to you on that.

Just had an email back from the lawyer to say that we are within our rights to withhold the final payment until act 16 has been served. I intend to visit again once they say it is finished but will request some up to date pics before I travel this time.

Incidentally, our contract states that we are also purchasing a percentage of the common areas. Surely then, it would need to be fully complete before the final payment is due. I have not heard anything about the mayor stopping all building. He has stopped approving any further plans as he feels the area is becoming overdeveloped. I have no doubt they will try and suggest some administration problems as this will negate a penalty. It would be interesting to see some documentary proof. While I was out in Bansko I spoke to another investor who said it is not unusual for a development to be late.
 
T

Tim Timovic

New Member
Olliesdad,
Thanks for the update. I also keep an eye on a different forum, 'Talk Bansko', and I've exchanged emails with a couple of investors from that site. They were worried that there was a conflict of interests issue with Ralitsa since she also represents agents selling the property.
Interesting point on withholding final pymt until act 16 - I'll check this out with my own lawyer.

Tim
 
O

olliesdad

New Member
Tim,

Thanks. Found the talk bansko site. Can't post email addresses or web links on this site so Ive done it on the talk bansko site. Will catch up with you on there.

Juliette, while I was there I spoke to a spokesman for the developer who states that C and D block will be finished in 2 weeks (end of Dec) and A and B will be finished at the end of Jan 08. Either he is dreaming, or he is scared of becoming part of the foundations for the next development because anyone can see that it will be more like March or April before the whole development is complete. I have spoken to Avatar who refer us to our legal reps and don't seem to want to get involved any more. typical agents!
 
J

Jain and Chris

Senior Member
Hi Bob

Thanks for doing that - I think the photos are lovely to be able to share with the others who are interested in this development.

I've checked the link and it's working fine, albeit a bit slow - probably because it's pictures.

All the best,
 
O

olliesdad

New Member
To Bob.

I've corrected the link. Should work now.

Many regards, thanks and merry christmas.

N.
 
T

Tim Timovic

New Member
Thanks for the photos Olliesdad. I can see that block A looks a long way off. We'll probably delay our own next visit until the spring.

Tim
 
Q

quinnn

New Member
Hi, has anyone bought in Panorama Casino & Spa in Bansko? There are delays in completion of blocks A & B & also some of the surrounding areas. Any info please? Thanks a lot
Hi, I have also bought in this development (block B) and am experiencing delays. The solicitor or agent have no useful info. Have you visited the development recently?? I have not been there since Feb 2007
 
I

indikai

New Member
Build Progress and Rental Plans for Panorama Casino

Hi, I have also bought in this development (block B) and am experiencing delays. The solicitor or agent have no useful info. Have you visited the development recently?? I have not been there since Feb 2007
Hi all. I've just picked this thread up as I was hunting for information on Panorama as I'm not just concerned about the delay in the build but I've been trying to access information on when, where, how and what is being advertised by the rental team. I've been looking for answers about the travel agency contracts they have in place that are ready for when this development has been finally completed. It feels bad enough to miss one season when everything should have been live but much worse to miss out on the opportunity of using this time pro-actively and advertising the complex. In short I don't think they've much established as my impression is that they're firefighting with other problems and lack of staff - I've bought in C Block but haven't paid as yet as my solicitor has requested a number or additional documents before we will send the money (I'm using a different solicitor to the one that Avatar recommended). I've had so many problems with my apartments in Sunny beach that I'm much less relaxed this time around-does anyone want to share e-mail address and write directly when we have any news or brainwaves connected to the Panorama??? Hope to hear from you soon.
 
Q

quinnn

New Member
Hi, I'm heading over on 13th Feb to see whats going on at the moment (not a lot from what I'm hearing!). Will give an update when I get back
Nichola
 
G

gabby

New Member
Panorama Block C

I also bought in Panorama Block C. My solicitor Vladimir Ivanov has POA and said act 15 had been signed. He also gave me a snagging report which did not include a lot! I was given the impression by both the solicitor and the devleoper that the site was nearly ready for opening. I have paid for the furniture and the property, also in advance for the rental with the developer. Has anybody else done the same? I also bought from Avatar. I wanted everythign sorted by end of year as the solicitor told me the POA would run out then as I had them signed by a notary in UK in August.

Gabby
 
G

gabby

New Member
I have left my e-mail address in Talk Bansko. There must be soemthing we can do about this. Could we contact a property mag??? Any other ideas???
 
G

gabby

New Member
This is the latest info form my solicitor I have as regards the situation

Developer is not inclined to voluntarily pay any penalties.

This is his attitude towards all of the Buyers in blocks C and D for the reason that Act 15 should have been issued on 31.10.2007 but it has been issued on 05.11.2007. In the Developer's opinion the delay of 5 days is insignificant.

The Development is under construction at the present moment but as we have indicated in our previous e-mails there is a lot of work on the common parts of the complex. We suupose it will be finished not earlier that April.
 
Status
Not open for further replies.
Top