oasistower2 march 2010
I met with Kamal at Oasis tower 2 in Dubai on 28th december 2009, I went to visit the site where I met the site project manager whom is Turkish, at this point no body from oasis was there just me my wofe and the project manager. He showed me the project plan which was on schedule to complete September 2011 however he said once his job is complete there is approx 4 months of testing and commissioning which is done by an approved body of dubai sport city.
Work on site was going on full steam however only 10 workers were there.
I went back to the oasis tower 2 office, which is the Buniah office in media city. There I met Kamal and I challenged him on the completion date, they said to me September I will have they keys I don’t believe them.
Kamal issued me with a new payment plan, I have already paid 70% so the new payment plan is based on
10% due when the 15th floor is completed
10% due when final floor is completed
10% on handover
However it is now March, I have emailed dubai oasis tower 2 3 times since January surprise surprise no reply, I have called them twice both times left message with the receptionist no one has yet called back.
I am totally pissed at the level of service being given and I still cant make my mind up on what I can legally do about it.