financier888
New Member
Hi Hatim1. I booked a 2 bedroom flat in The Garden City (Al Jurf) Ajman, Mandarine Tower M1. (Developer is Real Estate Investment Est.)
2. I started paying my monthly installments since Dec 2007. After paying the booking charges and advance in Nov 2007.
3. After every six months I visit them and give them 6 cheques for 6 monthly installments. So I have given them cheques till May 2009.
4. Till May 2009 I have paid Dhs. 125,082/-
5. Now, the contract clearly states completion date to be Dec 2009.
6. The tower M1 comprises of G+3P+12 Typical Floors and uptill now the have just put one ceiling of the ground floor (3P and 12 Floors are yet to be built).
7. Which means the completion date of Dec 2009 is impossible to be achieved (Also Seeing their progress of 19 months we can make out we can make out what they could do in the next 7 months.
8. The Contract binds both the parties, the buyer and the seller, to stick to all the clauses.
9. We are, on our part sticking to all the clauses of the Contract. But if the do not complete by Dec 2009, then this would clearly be against the contract.
10. The contract only allows them a delay in handing over if the authorities like FEWA etc. delays. But does not permit them a delay in construction.
11. On the basis of the above can I give a gap of 6 months in my installments to make my payments in line with their progress of work.
12. At the time of purchase of this property, they confidently told me that after Dec 2009 I can give the apartment on rent and pay the future installments with the rent amounts.
13. Is there any authority who can check the developers for abidig by the contract clauses.
Best Regards.
Hatimk
1) When it comes to May '09 - DO NOT GIVE THEM ANY MORE POST DATED CHECKS
2) Were you issued a SPA? (if so, the SPA should contain a provision for 'penalty' if the construction is delayed 'X'Time after original projected completion timeline
3) what % is your AED 125, 082 of the purchase price? 30 -40 -50% ?? (this is important
4) have they opened-up their escrow acct in Ajman yet?
5) be happy that the construction has started!! (many have not nor probably ever will!!!!) - you may be surprised how qiuckly the others floors can go up - as fast as one floor per 1 or 2 weeks depending on the amount of sq ftg... and the quality of their labour and if they will run two shifts....
Your only leverage will be when it comes to issuing the post dated checks - so dont....