Helpful information from Dubai Land Department RERA Hi ShacksT
The following statement is from RERA ( Landepartment Dubai) I got it from my friend , Senior project manager at Dubai Sports City who has bought property via Casa Dubai too.
Additionally I think you will be very interested to see the RERA information & links below
- particularly the following statement:
"With properties that are already being built, developers who have collected more than 20 per cent of the contract value from buyers will immediately have to stop asking for further payments until they correlate the escrow amounts already collected to construction progress."
Visit the RERA web site. It`s easy to find.
You`ll find many information regarding new laws, developer and theire progress with construction work and more.
I too have purchased through Casa Dubai and I just wondered if those of you who were getting together have managed to come up with a plan? I do not live near London so I would be unable to meet up with you.
After finding out about Casa Dubai I contacted Chapal as I have a unit on the Destiny and I wanted to find out what my options are as i was advised (not by the developer) that there is up to an 18 month delay on the completion.
Having contacted Chapal they tell me I cannot delay my future payments in line with this and that this is in the contract. I have paid just over 25% and I have yet to receive a contract.
Considering all the bad press I have been reading lately I feel there is no certainty that Chapal will even complete the development and it will be shelved like many others.
I am unsure of my rights and wondered if anyone can advise me of what they are and what I should do.
The payment plan I signed up for was that I paid 50% up to completion and the rest over a further five years.