S
sk302016
New Member
In my opinion, I feel the term "construction started" is very tricky and Dubai authority must well define what is "construction started" and also "construction progress" together. I strongly recommend Dubai authority use and execute the term "construction program" instead of "construction started".
Nowadays, here are how developers did and think and define about "construction started" (and construction progress). Any of the following items count "Started" (and progress) from the point of view of some developers.
1. project launched in 2005 and tell buyers that they are still evaluating constractor in 2008.
2. project launched in 2005 and tell buyers that they have not received land and permission from the master developer in 2008
3. put fence on the construction site, some site don't even have project board there.
4. put crane and a few of construction material on site but no movement happened for a year. I heard some of the crane are broken, just for show.
5. some workers play sand once a while, just for show
6. workers move tool and machine from here to there on site and did nothing about construction
7. spent years on planning papers after launch. The "Started" (and progress) is those "planning papers".
8. spent years for pile testing
9. spent years to dig a hole on ground
The result of above cause "DELAY". Some of us might already agreed and signed addendum with developers for changing the completion date and long-stop date (and other terms stay the same as shown on the original contract). But, in many cases, it looks like that the developer still can not finish it with new date. So, buyers are either expecting and agree the 2nd addendum (maybe 3rd, 4th...) for changing date again or ask for compensation if you don't agree for changing date from the beginning (but you must make all payment on time from the beginning). I wonder anyone here who already receive compensation from any developer. I look compensation in this way: compensation = discount (deduct from your last payment) = bank interest = you lose rental income (higher than bank interest) = you lose capital gain = stuck your money for a long time. The compensation is just better than zero from investment point of view.
Concerning "construction program", it is more specific with detail work plan, such as when the foundation will be finished, when the 10th floor will be finished, when the last floor will be finished and so on. Every construction project in the world should come with a construction program and time frame/table. It makes sense for everyone including developers. In my country, construction program is a part of contract and developer collect payment (also send photo to buyers as proof) whenever the progress reach there. In Dubai, some developers just drop you "anticipate completion date" then change it later without explanation.
Without a transparent "construction program", in some cases, I personally think that we are either wait for a unkown long time (probably until developer have enough cash to go on) or the developer go bankrupt sooner or later. However, it could take forever to finish it or maybe a never ending story if workers work 2 days and take three days off. It is decision of developer. We have no choice about their decision and plan.
Thanks for reading my post.
All the best,
Nowadays, here are how developers did and think and define about "construction started" (and construction progress). Any of the following items count "Started" (and progress) from the point of view of some developers.
1. project launched in 2005 and tell buyers that they are still evaluating constractor in 2008.
2. project launched in 2005 and tell buyers that they have not received land and permission from the master developer in 2008
3. put fence on the construction site, some site don't even have project board there.
4. put crane and a few of construction material on site but no movement happened for a year. I heard some of the crane are broken, just for show.
5. some workers play sand once a while, just for show
6. workers move tool and machine from here to there on site and did nothing about construction
7. spent years on planning papers after launch. The "Started" (and progress) is those "planning papers".
8. spent years for pile testing
9. spent years to dig a hole on ground
The result of above cause "DELAY". Some of us might already agreed and signed addendum with developers for changing the completion date and long-stop date (and other terms stay the same as shown on the original contract). But, in many cases, it looks like that the developer still can not finish it with new date. So, buyers are either expecting and agree the 2nd addendum (maybe 3rd, 4th...) for changing date again or ask for compensation if you don't agree for changing date from the beginning (but you must make all payment on time from the beginning). I wonder anyone here who already receive compensation from any developer. I look compensation in this way: compensation = discount (deduct from your last payment) = bank interest = you lose rental income (higher than bank interest) = you lose capital gain = stuck your money for a long time. The compensation is just better than zero from investment point of view.
Concerning "construction program", it is more specific with detail work plan, such as when the foundation will be finished, when the 10th floor will be finished, when the last floor will be finished and so on. Every construction project in the world should come with a construction program and time frame/table. It makes sense for everyone including developers. In my country, construction program is a part of contract and developer collect payment (also send photo to buyers as proof) whenever the progress reach there. In Dubai, some developers just drop you "anticipate completion date" then change it later without explanation.
Without a transparent "construction program", in some cases, I personally think that we are either wait for a unkown long time (probably until developer have enough cash to go on) or the developer go bankrupt sooner or later. However, it could take forever to finish it or maybe a never ending story if workers work 2 days and take three days off. It is decision of developer. We have no choice about their decision and plan.
Thanks for reading my post.
All the best,
Last edited: